Bolivia

EL CARRIZAL HYDROELECTRIC POWER PLANT

Client

Bolivian National Electricity Company (ENDE).

Year

2018

Key facts

Hydroelectric power plant with 3 generating units. Gross head: 850 m. Total turbine flow: 51 m3/s. Power: 366 MW. Roller-compacted concrete dam, 160 m high, with a crest length of 379.5 m. Spillway design flow: 3,994 m3/s. 220/13,8 kV high voltage step-up substation and 96 km long high-voltage transmission line.

Services

Final design, geological and seismic site studies, inlcuding field works and a pilot gallery for testing.
12.CarrizalWEB

El Carrizal hydroelectric power system, Bolivia

Ende (National Electricity Company of Bolivia) engaged Asociación AH Carrizal, with TYPSA as the lead partner, to develop the Carrizal Hydroelectric Project. The Project’s main...

INTEGRITY COMMUNICATION CHANNEL

  • Data controller: TECNICA Y PROYECTOS, S.A
  • Purpose: your data will be used to process your request and provide you with our services.
  • Lawful basis for processing: the consent of the person concerned.
  • Legal rights: you have the right to know what data is stored about you, to correct it and ask for it to be deleted, as explained in the additional information available on our website.
  • Additional information: more information can be found in the ‘Privacy policy’ section of our website.