Spain

Alicante-Elche Miguel Hernández Airport New terminal

Client

AENA

Year

2011

Construction budget

EUR 308 million

Key facts

Gross area of 455,500 m².

Capacity: >14 MPAX annual

Terminal building: 333,000 m² with 98 check-in counters, 26 boarding gates, 15 telescopic walkways, SATE, bus station, pneumatic waste collection system and thermo-cooling plant.

The building’s roof is made up of 40 domes, each 36 metres in diameter.

In addition to 122,500 m² parking with 4,200 parking spaces.

Services

Construction engineering and construction supervision services.

INTEGRITY COMMUNICATION CHANNEL

  • Data controller: TECNICA Y PROYECTOS, S.A
  • Purpose: your data will be used to process your request and provide you with our services.
  • Lawful basis for processing: the consent of the person concerned.
  • Legal rights: you have the right to know what data is stored about you, to correct it and ask for it to be deleted, as explained in the additional information available on our website.
  • Additional information: more information can be found in the ‘Privacy policy’ section of our website.