Argentina

LOMA BLANCA I, II, III, VI WIND FARMS

Client

Goldwind International

Year

2020

Construction budget

USD 500 million

Key facts

Loma Blanca I: 50MW, 16 x GW140-3.2MW, HH100

Loma Blanca II: 50MW, 16 x GW140-3.2MW, HH100

Loma Blanca III: 50MW, 16 x GW140-3.2MW, HH100

Loma Blanca VI: 100MW, 32 x GW140-3.2MW, HH100

132/33 kV air insulated generation substation (AIS), single busbar arrangement with one line bay and two transformer bays, two 60 MVA power transformers and 6 collector lines (Loma Blanca I-III)

40 km 132 kV HV double circuit overhead line to connect the generation substation and the TRANSBA Puerto Madryn 500/132 kV substation (Loma Blanca I-III)

132/33 kV air insulated generation substation (AIS), single busbar arrangement with one line bay and two transformer bays, two 60 MVA power transformers and 6 collector lines (Loma Blanca VI)

34 km 132 kV HV single circuit overhead line to connect the generation substation and the TRANSBA Puerto Madryn 500/132 kV substation (Loma Blanca VI)

Services

Owner’s engineering including tender engineering, support during the bidding process, preparation of the Terms of Reference, contractor selection and evaluation and preparation of the EPC contract technical appendices. Review of contractor’s engineering, project quality management, project management support, construction schedule management and construction management.

INTEGRITY COMMUNICATION CHANNEL

  • Data controller: TECNICA Y PROYECTOS, S.A
  • Purpose: your data will be used to process your request and provide you with our services.
  • Lawful basis for processing: the consent of the person concerned.
  • Legal rights: you have the right to know what data is stored about you, to correct it and ask for it to be deleted, as explained in the additional information available on our website.
  • Additional information: more information can be found in the ‘Privacy policy’ section of our website.